The challenge
Project teams repeatedly reconstructed field-change events from reports, photographs, tickets and email before internal commercial review could begin.
What Blackwood did
Blackwood implemented controlled intake, linked supporting records, factual event chronologies, completeness checks and an exception queue, with named project-manager approval before handoff.
The outcome
In the reported 90-day operating period, median event-to-review-ready time fell from 44 to 8.5 business hours. First-review complete packets increased from 46% to 92%.
Scope and limits
Review readiness is not an approved change order. The workflow did not determine entitlement, price work, approve schedule impacts or establish improved project profit.
Concise summary of Blackwood Enterprises case study 005, publication version 1.0. Reported results relate to this engagement and do not guarantee future outcomes.